Progress report for 12/15/14

Highlights from DLR Group’s Field Observation Report 65: At the book detector, the Moxie panels have been removed and the frames have been repainted At the acoustical accent walls; – the installation and painting of the steel trim has been … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 12/15/14

Progress report for 12/3/2014

Highlights from DLR Group’s Field Observation Report 64: The pipe bollards around the patio have been painted The Moxie panels have been installed to the frames at the book detector Work to install and paint the steel trim on the … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 12/3/2014