Monthly Archives: October 2014

Progress report for 10/22/14

Highlights from DLR Group’s Field Observation Report 58: Work on the ceiling will continue after the installation of the Terrazzo flooring has been completed Installation of the Axiom trim around the Tectum ceiling has begun The drywall sub is performing … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 10/22/14

October 21, 2014, photo update (click a photo to enlarge it)

     

Posted in Uncategorized | Comments Off on October 21, 2014, photo update (click a photo to enlarge it)

Progress report for 10/15/14

Highlights from DLR Group’s Field Observation Report 57: Work to complete the installation of the metal ceiling over the entry area is pending the resolution of how to attach the light fixtures to the grid Work to install the forms for … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 10/15/14

Progress report for 10/8/14vvvv

Highlights from DLR Group’s Field Observation Report 56: Work to complete the installation of the metal ceiling over the entry area is pending the resolution of how to attach the light fixtures to the grid The repairs to the track for … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 10/8/14vvvv

Progress report for 10/1/14

Highlights from DLR Group’s Field Observation Report 55: The ceramic tile installation to the walls tile in the public restrooms, janitor closet and family restroom has been done The plumbing fixtures are in place in the public restrooms and the … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 10/1/14