Progress report for 4/9/14

Highlights from DLR Group’s Field Observation Report 33:

  • Work on the roof includes installation of the mechanical equipment curb over the north mechanical room – installation of the backer rod and sealant to the building expansion joint in the fascia panel on the north side of the clerestory – application of the mesh tape and coating to the seams of the metal roof panels and along the sill of the clerestory windows
  • Work on the metal framing for the gypsum walls and soffits over the circulation area is in progress
  • Gypsum board has been hung on the study room walls
  • Tape and coat of the gypsum board is ongoing throughout the project
  • The acoustic sound panels for the ceiling have been delivered and stacked in the center of the room
  • The electrical sub is installing the cable trays
  • The Work to relocate the chilled water lines along the north end is in progress
  • The new air handler number 2 has been installed in the north mechanical room and the hydronic lines are being extended to the new connection points
  • Work to install the steel knife plates to the acoustic walls is in progress
  • The concrete floor has been cut and removed at the interior glazing channel locations

 

New air handler set in place

New air handler set in place

Exterior paint mock-up

Exterior paint mock-up

Framing over circulation area

Framing over circulation area

Work on roof to seal clerestory windows

Work on roof to seal clerestory windows