Monthly Archives: March 2014

Progress report for 3/12/14

Highlights from DLR Group’s Field Observation Report 28: Structural steel track for the exterior framing at the East entry has been installed. The final concrete pour on the East side of the library was complete. Structural steel track on the … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 3/12/14

Progress report for 3/5/14

Highlights from DLR Group’s Field Observation Reports 26 and 27: The steel columns, beams and steel trellis for the entry canopy have been installed. T.S. joists are on site and are in the process of being welded in place. Metal deck … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 3/5/14