Monthly Archives: January 2014

Progress report for 1/8/14

Highlights from DLR Group’s Field Observation Report 19: Conduit for data and AV has been installed over the East main entry. Miscellaneous pours of concrete were completed throughout. These include study room 407 and Staff Lounge 438. Steel supports for the … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 1/8/14

Progress report for 1/2/14

Highlights from DLR Group’s Field Observation Report 18: The majority of the concrete within the building has been poured. There are still two pours remaining. The East side of the library adjacent to the main entrance and miscellaneous pours for floor box … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 1/2/14

Progress report for 12/18/13

  Highlights from DLR Group’s Field Observation Report 17: Soffit framing within and around the classrooms is in process. Steel beams to support the NanaWall assembly have been installed at the classrooms. Soffit framing adjacent to the electric water coolers … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 12/18/13