Monthly Archives: December 2013

Progress report for 12/11/13

Highlights from DLR Group’s Field Observation Report 15: Electrical in-wall rough-in has been completed on East side of building. Metal strapping for wall mounted flat screens has been installed. IT to review power and data at these locations and sign off … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 12/11/13

Progress report for 12/3/13

Highlights from DLR Group’s Field Observation Report 14: Trenching for the fireline is in progress. Excavation is complete for grade beams at new storefront pop outs on the East elevation. The main ductwork installation from the mechanical room through the … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 12/3/13