Progress report for 10/23/13

Highlights from DLR Group’s Field Observation Report 8: Holes have been drilled in existing grade beams for installation of epoxy adhesive anchors to tie in new grade beams on North and South elevations. Saw cutting for new waste piping on East … Continue reading

Posted in Uncategorized | Comments Off on Progress report for 10/23/13

Progress report for 10/17/13

Framing work was scheduled to begin at the end of the week.